Send this document to a colleague |
Close
This Window |
|
No. 04-02-00808-CV
ALAMO COMMUNITY COLLEGE
DISTRICT,
Appellant
v.
BROWNING CONSTRUCTION COMPANY,
Appellee
From the 407th Judicial District Court, Bexar County,
Texas
Trial Court No. 2000-CI-05250
Honorable Karen Pozza, Judge Presiding Opinion
by:
Karen Angelini, Justice Sitting: Catherine Stone,
Justice Paul W. Green, Justice Karen Angelini, Justice Delivered
and Filed:
January 14, 2004 AFFIRMED This
case arises from a breach-of-contract suit between Browning Construction
Company (ABrowning@)
and Alamo College Community District (AACCD@). At trial, the jury awarded
Browning, the plaintiff, over $3,000,000 on its breach-of-contract claim.
The trial court entered judgment in accordance with the verdict. ACCD, the
defendant at trial, appeals the judgment of the trial court in fourteen
issues. Browning, appellee and cross-appellant,
brings one issue on appeal. We affirm the judgment of the trial
court. Background ACCD
and Browning entered into a contract whereby Browning agreed to serve as
the general contractor for the construction of a new campus for ACCD.
After disagreements over delay, Browning sued ACCD for breach of contract
and won damages of over $3,000,000. The key issue in the suit was whether
Browning could collect damages for delay when the contract had a
no-damages-for-delay clause. The jury answered yes, because 1) ACCD had
waived its right to rely on that clause; 2) ACCD is estopped from relying on that clause; 3) ACCD and
Browning had agreed to modify the clause; 4) the delays encountered by
Browning were caused by the active interference of ACCD; 5) ACCD committed
unreasonable delay such that Browning would have been justified in
abandoning the contract; and 6) ACCD committed fraud, misrepresentation,
or other bad faith. Browning also sued ACCD for violations of the Prompt
Pay Act and quantum meruit. The jury did not
find for Browning on these causes of action. ACCD,
appellant and cross-appellee, presents the
following issues for review: 1)
Does sovereign immunity protect ACCD from suit? Does sovereign immunity
protect ACCD from tort liability? 2)
Did ACCD have a duty to Browning for design errors? 3)
Was it proper for the trial court to instruct the jury that the architects
were agents of ACCD? 4)
Was it error for the trial court to permit the jury to assess damages for
Browning=s
liability to its subcontractors? 5)
Does Jury Question 5 submit an offensive theory of estoppel, and if so, was it error for the trial court
to submit it? 6)
Was it error for the trial court to omit from Jury Question 1 an
instruction on the specific contractual provisions at issue? Does Jury
Question 1(b) violate Casteel? 7)
Did the trial court submit an improper measure of damages? 8)
Was there legally and factually sufficient evidence of causation to
support a finding of damages for delay? 9)
Was there legally and factually sufficient evidence of consideration to
support the jury=s
finding that ACCD and Browning agreed to modify the
contract? 10)
Was there legally and factually sufficient evidence of design
error? 11)
Did the trial court abuse its discretion in denying ACCD=s
motion for new trial? 12)
Was there legally and factually sufficient evidence to support the
jury=s
finding that ACCD waived its right to rely on the no-damages-for-delay
clause as a defense to Browning=s
claims? 13)
Was there legally and factually sufficient evidence to support the
jury=s
finding that ACCD breached the contract? 14)
Was there legally and factually sufficient evidence to support the
jury=s
finding of overhead cost damages?
Browning,
appellee and cross-appellant, presents the
following issue for review: Did the trial court err in failing to render
judgment notwithstanding the verdict for Browning on its Prompt Pay Act
claim? Sovereign
Immunity A.
Immunity from Suit In
its first issue, ACCD argues that sovereign immunity protects it from
suit. Sovereign
immunity defeats a trial court=s
subject-matter jurisdiction over a lawsuit. Tex. Dep=t
of Transp. v. Jones, 8 S.W.3d 636, 638-39
(Tex. 1999) (per curiam). The State may assert
sovereign immunity from suit in a plea to the jurisdiction. Id. at
638. Because the question of subject-matter jurisdiction is a question of
law, we review de novo a trial court=s
order denying a jurisdictional plea based on sovereign immunity. Mayhew
v. Town of Sunnyvale, 964 S.W.2d 922, 928 (Tex. 1998). ACCD
argues that sovereign immunity protects it from suit. We have specifically
held, however, that junior college community districts like ACCD are
not immune from suit: ACCD
is a junior college community district organized pursuant to chapter 130
of the Texas Education Code. Under chapter 130, ACCD=s
board of trustees=
Apowers
and duties@
Ain
the . . . management and control of the junior college@
are governed by Athe
general law governing the . . . management and control of independent
school districts insofar as the general law is applicable.@
Part of the Ageneral
law@
governing the management and control of independent school districts is
the Texas Legislature=s
consent to suits against A[t]he
trustees of an independent school district . . . in the name of the
district . . . .@ . . . By
subjecting junior college districts like ACCD to
the same general law applicable to independent school districts, it
appears to us, clearly and unambiguously, the Texas Legislature granted
its consent to sue junior college community districts and we so
hold. Alamo
Cmty. Coll. Dist. v. Obayashi Corp., 980
S.W.2d 745, 747-48 (Tex. App.CSan
Antonio 1998, pet. denied) (citations omitted), abrogated on other
grounds by Gen. Servs. Comm=n
v. Little-Tex Insulation Co., 39 S.W.3d 591, 595-98 (Tex.
2001). In
Obayashi, we followed the supreme court=s
holding in Missouri Pacific Railroad Co. v. Brownsville Navigation
District, 453 S.W.2d 812 (Tex. 1970). See Obayashi, 980 S.W.2d
at 748 (citing Mo. Pac., 453 S.W.2d at 813). In Missouri
Pacific, the question was whether a 1925 statute clearly and
unambiguously waived Brownsville Navigation District=s
immunity from suit. Mo. Pac., 453 S.W.2d at 813. The statute
provided: AAll
navigation districts established under this Act may, by and through the
navigation and canal commissioners, sue and be sued in all courts
of this State in the name of such navigation district . . . .@
Id. (emphasis added). The court held: AIn
our opinion [the statute] is quite plain and gives general consent for
District to be sued in the courts of Texas in the same manner as other
defendants.@
Id. Similarly,
the statute we relied on in Obayashi provides: AThe
trustees of an independent school district constitute a body corporate and
in the name of the district may acquire and hold real and personal
property, sue and be sued, and receive bequests and donations or
other moneys or funds coming legally into their hands.@ Tex. Educ.
Code Ann. '
11.151(a) (Vernon 1996) (emphasis added). Thus, both Obayashi and
Missouri Pacific find a waiver of sovereign immunity where the
Legislature provides that the governmental entity may Asue
and be sued.@
Mo. Pac., 453 S.W.2d at 813; Obayashi, 980 S.W.2d at
748. ACCD
argues that two recent Texas Supreme Court cases, Texas Natural
Resource Conservation Commission v. IT-Davy, 74 S.W.3d 849 (Tex. 2002)
and Travis County v. Pelzel & Associates,
Inc., 77 S.W.3d 246 (Tex. 2002), suggest that community college
districts like ACCD are immune from suit. We disagree.
In
IT-Davy, a general contractor (IT-Davy) contracted with the Texas
Water Commission (predecessor of the Texas Natural Resource Conservation
Commission) to clean up a hazardous waste site in Houston. IT-Davy, 74 S.W.3d at 851.
IT-Davy cleaned the site, and the TNRCC paid IT-Davy the full contract
price. Id. IT-Davy claimed, however, that it was owed
additional monies under the contract because materially different
site conditions increased its clean‑up costs. Id. The TNRCC refused
to pay these additional costs, and IT-Davy brought suit against the TNRCC
for breach of contract, negligent misrepresentation, quantum meruit, and promissory estoppel. Id. at 851-52. In response, the TNRCC
filed a plea to the jurisdiction, alleging that sovereign immunity barred
IT-Davy=s
claims. Id. at 852. The trial court denied the plea. Id. The
TNRCC then filed an interlocutory appeal. Id. The court of appeals
affirmed the trial court=s
order, holding that IT‑Davy=s
allegations were Asufficient
to show that the [TNRCC] has engaged in conduct, beyond the mere execution
of a contract, that waives its immunity from suit.@
IT-Davy, 74 S.W.3d at 851 (citation omitted) (brackets in
original). At
the supreme court, IT‑Davy argued that the TNRCC waived its immunity from
suit by fully accepting benefits under the contract. Id. at 856. In
support of its argument, IT-Davy cited a footnote from Federal
Sign v. Texas Southern
University, 951 S.W.2d 401 (Tex. 1997), providing that there may be
circumstances Awhere
the State may waive its immunity by conduct other than simply executing a
contract . . . .@
See IT-Davy, 74 S.W.3d at 856 (quoting Federal Sign, 951
S.W.2d at 408 n.1). Thus, the issue for the supreme court in
IT-Davy was whether Texas law allows governmental entities to waive
their immunity by conduct. See id. (noting that several courts of
appeals have relied on the footnote in Federal Sign to create a
judicially-imposed, equitable waiver of immunity from suit). The court
held: We
again affirm that it is the Legislature=s
sole province to waive or abrogate sovereign immunity. . . . Because we
have consistently held that only the Legislature can waive sovereign
immunity from suit, allowing other governmental entities to waive immunity
by conduct that includes accepting benefits under a contract would be
fundamentally inconsistent with our established jurisprudence and with the
existing legislative scheme. Accordingly, we reject IT-Davy=s
argument that we should fashion such a waiver-by-conduct exception in a
breach-of-contract suit against the State. Id.
at 857 (emphasis added). The
court also found that the TNRCC=s
sovereign immunity was not waived by contract, legislative consent under
sections 5.351 and 5.352 of the Texas Water Code, or legislative consent
in the Declaratory Judgment Act. Id. at
856. In
the case before us, Browning does not argue that ACCD waived its immunity
by conduct. Accordingly, the
waiver-by-conduct holding of IT-Davy does not apply here.
Additionally, nowhere does the IT-Davy court address sovereign
immunity for community college districts under the Texas Education Code,
the issue in this case. Rather, IT-Davy reaffirms that it is the
Legislature=s
sole province to waive sovereign immunity. Id. at 857. We found in
Obayashi that the Legislature waived sovereign immunity for
community college districts by enacting sections 130.084 and 11.151(a) of
the Texas Education Code. Obayashi, 980 S.W.2d at 747-48.
Accordingly, with respect to waiver by statute, Obayashi and
IT-Davy are entirely consistent. ACCD
next argues that the Pelzel case suggests
that community college districts like ACCD are immune from suit. In Pelzel, a construction company (Pelzel) sued Travis County for breach of contract,
seeking monies allegedly due under the contract. Pelzel, 77 S.W.3d at 247. Travis County filed a
plea to the jurisdiction, alleging sovereign immunity. Id. The
trial court denied the plea. Id. Travis County brought an
interlocutory appeal, and the court of appeals affirmed the trial
court=s
order, concluding that Travis County waived its immunity by conduct.
Id. at 247-48. The court of appeals further concluded that
because Pelzel complied with section 89.004 of
the Texas Local Government Code by presenting its claim to the county
commissioners court before filing suit, the trial court had jurisdiction.
Id. at 247 (citation omitted). Section 89.004 provides:
A[A]
person may not file suit on a claim against a county . . . unless the
person has presented the claim to the commissioners court and the
commissioners court neglects or refuses to pay all or part of the claim. .
. .@
Tex. Loc. Gov=t Code Ann. '
89.004(a) (Vernon Supp. 2003). Thus, the issue for the supreme court in
Pelzel was whether the
presentment-of-claim language in section 89.004 clearly and unambiguously
waives Travis County=s
immunity from suit. The court held: AThis
statutory language does not clearly and unambiguously waive immunity from
suit.@
Pelzel, 77 S.W.3d at 249. The court goes
on to cite statutes that do clearly and unambiguously waive
immunity from suit. See id. (citing, as an example of a
clear and unambiguous waiver of suit, section 101.025(a) of the Texas
Civil Practices and Remedies Code, which provides that A[s]overeign immunity to suit is waived and abolished to
the extent of liability created by this chapter@).
The court also distinguishes section 89.004(a) from the statute preceding
it, stating: AOriginally,
the statute contained >sue
and be sued=
language, arguably showing intent to waive sovereign immunity for suits
against counties.@
Id. at 249-50 (citing Mo. Pac., 453 S.W.2d at
813). ACCD
relies on this language to support its argument that ACCD is immune from
suit. As shown by the direct quote above, however, Pelzel does not resolve the question whether
Asue
and be sued@
language waives sovereign immunity. Id. Nor does Pelzel overrule Missouri Pacific.
Id. We are bound by the authority of Missouri Pacific unless
the supreme court overrules it. Penrod
Drilling Corp. v. Williams, 868 S.W.2d 294, 296 (Tex. 1993); In re
K. S., 76 S.W.3d 36, 49 (Tex. App.CAmarillo
2002, no pet.). Accordingly, we must continue to follow Missouri
Pacific. We
recognize that the Fifth Court of Appeals has interpreted IT-Davy
and Pelzel to mean that the
Legislature did not intend to waive sovereign immunity for school
districts. See Satterfield & Pontikes Constr., Inc. v.
Irving Indep. Sch.
Dist., No. 05‑03‑00004‑CV, 2003 WL 22221024, at *2 (Tex. App.CDallas
Sept. 26, 2003, no pet. h.) (holding that the Asue
and be sued@
language in section 11.151 of the Texas Education Code merely speaks to
the City=s
capacity to sue and its capacity to be sued when immunity has been
waived). The effect of the court=s
decision, however, is to improperly overrule Missouri Pacific.
Satterfield, 2003 WL 22221024, at *17 (Lang, J., dissenting).We
believe that we are bound by Missouri Pacific unless the supreme
court overrules it. Therefore, we reiterate our
holding in Obayashi and hold that because the Legislature clearly
and unambiguously waived immunity for community college districts, ACCD is
not immune from suit. Obayashi, 980 S.W.2d at 748. Accordingly, we
overrule this issue on appeal. B.
Immunity from Liability ACCD
next argues that sovereign immunity protects it from
liability. Immunity
from liability protects the state from judgment, even if the legislature
has expressly consented to suit. Tex. Dep=t
of Transp. v. Jones, 8 S.W.3d 636, 638 (Tex.
1999) (per curiam). Generally, junior college
districts are not subject to tort liability for property damage, personal
injury, or death caused by the wrongful act or omission or the negligence
of an employee, except when the claim involves a motor vehicle. Tex. Civ.
Prac. & Rem. Code
Ann. ' 101.001(3)(B) (Vernon Supp.
2002); '' 101.021, 101.051 (Vernon
1997). ACCD argues,
therefore, that ACCD is immune from the fraud claims for which it was
found liable in Jury Question 11. Jury
Question 11, however, is not a fraud question. Rather, it asks whether
ACCD=s
fraud caused the delays. (The jury=s
answer of Ayes@
prevents ACCD from relying on its no-damages-for-delay clause.) Nowhere in
Browning=s
petition does it assert a cause of action for fraud. Also, contrary to
ACCD=s
assertion, the damages the jury assessed against ACCD are based solely on
breach of contract. Because
fraud is not a cause of action in the case, there are no fraud damages
from which to find ACCD immune. Accordingly, we overrule ACCD=s
immunity-from-liability issue. Duty for Design
Errors The
jury assessed $2,624,802.51 in damages against ACCD because it found ACCD
breached the contract in several ways, including failing or refusing to
correct design errors.[1]
ACCD argues that these damages are unenforceable because the contract does
not impose a duty on ACCD for such design errors. Thus, the issue turns
upon interpretation of the contract. Interpretation
of an unambiguous contract is a question of law and we are not required to
defer to any interpretation afforded by the trial court. MCI Telecomms. Corp. v. Tex. Utils. Elec. Co., 995 S.W.2d 647, 650 (Tex. 1999);
Birnbaum v. Swepi LP, 48 S.W.3d 254, 257 (Tex. App.CSan
Antonio 2001, pet. denied). Accordingly, we review the trial court=s
construction of an unambiguous contract de novo. MCI, 995
S.W.2d at 651. Texas
law provides: A[U]nless so expressed in the contract, an owner that
furnishes a prime contractor plans and specifications is not a guarantor
of the sufficiency of the plans and specifications.@
See City of San Antonio v. Forgy, 769
S.W.2d 293, 297 n.1 (Tex. App.CSan
Antonio 1989, writ denied) (citing Lonergan v. San Antonio Loan & Trust
Co., 101 Tex. 63, 104 S.W. 1061 (1907)). Texas law further
provides: If
there be any obligation resting upon the [owner], as guarantor of the
sufficiency of the specification, it must be found expressed in the
language of the contract, or there must be found in that contract such
language as will justify the court in concluding that the parties intended
that the [owner] should guarantee the
sufficiency of the specifications to [the
contractor]. Lonergan, 104 S.W. at 1066.
Here,
the contract between ACCD and Browning provides: The
Contractor shall carefully study and compare the Contract Documents with
each other and with information furnished by the Owner pursuant to
Subparagraph 2.2.2 and shall at once report to the Architect errors,
inconsistencies or omissions discovered. The Contractor shall not be
liable to the Owner or Architect for damage resulting from errors,
inconsistencies or omissions discovered. The Contractor shall not be
liable to the Owner or Architect for damage resulting from errors,
inconsistencies or omissions in the Contract Documents unless the
Contractor recognized such error, inconsistency or omission and failed to
report it to the Architect. If the Contractor performs any construction
activity knowing it involves a recognized error, inconsistency or omission
in the Contract Documents without such notice to the Architect, the
Contractor shall assume appropriate responsibility for such performance
and shall bear an appropriate amount of the attributable costs for
correction. This
paragraph indicates that ACCD was to be responsible for design errors.
Additionally, it is nearly identical to language that the Fourteenth Court
of Appeals found Aintended
that the owner guarantee the sufficiency of the specifications.@
N. Harris County Junior Coll. Dist. v. Fleetwood Constr. Co., 604 S.W.2d 247, 253 (Tex. Civ. App.CHouston
[14th Dist.] 1980, writ ref=d
n.r.e.). In Fleetwood, the contract
provided: The
Contractor shall carefully study and compare the Contract Documents and
shall at once report to the Architect any error, inconsistency or omission
he may discover. The Contractor shall not be liable to the Owner or the
Architect for any damages resulting from any such errors, inconsistencies
or omissions in the Contract Documents. Id. Because
the contract in this case contains language indicating ACCD had a duty to
Browning for design errors, we overrule ACCD=s
second issue. Agency The
jury instructions in this case provided: AACCD
means Alamo Community College District, the owner of the project and the
defendant in this lawsuit, and its agents, including Beaty Sanders Chesney
Morales & Fly, a Joint Venture, the architects on this project.@
ACCD argues that the trial court erred in so instructing the jury because
1) Browning did not plead the architects as agents; and 2) it was improper
for the trial court to instruct the jury that the architects were agents
as a matter of law rather than submitting agency as a fact question
for the jury to answer. We
review whether an instruction properly instructed the jury on a matter of
law de novo. M. N. Dannenbaum,
Inc. v. Brummerhop, 840 S.W.2d 624,
631 (Tex. App.CHouston
[14th Dist.] 1992, writ denied) (asserting that an instruction is improper
if it misstates the law); Villareal v.
Reza, 236 S.W.2d 239, 241 (Tex. Civ.
App.CSan
Antonio 1951, no writ) (finding an instruction that fails to instruct the
jury on the burden of proof issue erroneous). A
party alleging agency has the burden of pleading and proving the agency
relationship. S. County Mut. Ins. Co. v.
First Bank & Trust, 750 S.W.2d 170, 172 (Tex. 1988). If no special
exceptions are filed, we must construe the pleadings liberally in favor of
the pleader. Horizon/CMS Healthcare Corp. v. Auld, 34 S.W.3d 887,
897 (Tex. 2000). Here, Browning alleged AACCD
and its Architect@
in its petition. This language shows that Browning was seeking to hold
ACCD liable for the wrongful acts of its architects. Moreover, ACCD failed
to file special exceptions, so we must construe the pleadings liberally in
favor of the pleader. Id. Accordingly, we find that Browning did
plead the architects as agents. Second,
Texas law provides that whether an agency relationship exists is a
question of fact unless the evidence establishes the relationship as a
matter of law. Bhalli v. Methodist
Hosp., 896 S.W.2d 207, 210 (Tex. App.CHouston
[1st Dist.] 1995, writ denied). A court can determine, as a matter of law,
the existence of an agency relationship from an agreement between the
parties. Ward v. Prop. Tax Valuation, Inc., 847 S.W.2d 298, 300
(Tex. App.CDallas
1992, writ denied). An
Aagent@
is one who is authorized by a person or entity to transact business or
manage some affair for the person or entity. Tenn.‑La. Oil Co. v.
Cain, 400 S.W.2d 318, 325 (Tex. 1966). Here, the contract provides
that the architects are authorized to do the following: 1) review and
certify amounts due the contractor and issue certificates for payment in
such amounts; 2) reject work that does not conform to contract documents;
3) review and approve or take other action on submittals, including shop
drawings, product data, and samples; 4) prepare change orders and
directives; 5) conduct inspections to determine dates of substantial and
final completion; and 6) interpret and decide matters concerning
performance under the contract and concerning the requirements of the
contract. Because the contract provides that the architects are authorized
to act on behalf of ACCD, the contract establishes the agency relationship
as matter of law. Accordingly, we overrule ACCD=s
third issue. Active
Interference by Agents Jury
Question 7 provides: AWere
the delays encountered by Browning on the Project caused by the active
interferences by ACCD or its agents and/or Architects?@
The jury=s
answer of Ayes@
prevents ACCD from relying on its no-damages-for-delay
clause. ACCD
argues that this question is improper because the law does not extend the
Aactive
interference@
exception to agents. The case ACCD cites for this proposition, however,
deals with two issues: 1)
whether the requirement of conspicuousness applies to no-damages-for-delay
clauses (the court said no); and 2) whether a judgment predicated on
exceptions to a damages-for-delay clause can stand when none of the
specific exceptions were presented to the jury either by issue or
instruction (again, the court said no). Green Int=l, Inc.
v. Solis, 951
S.W.2d 384, 386-88 (Tex. 1997). The case does not address whether the
Aactive
interference@
exception applies to acts of the agent. Thus, ACCD has failed to present
any authority for its argument. Because
ACCD has offered (and we find) no legal authority for its argument, we
overrule this issue on appeal.
Insurance ACCD
next argues that the trial court erred in allowing Browning to make
references to the architect=s
insurance coverage. ACCD points us to two places in the record where
insurance is allegedly mentioned.[2] ACCD failed, however, to object in either instance.
Accordingly, it has waived error. Tex. R. App. P. 33.1 (a)(1). ACCD suggests that these references to insurance are
incurable error, implying it did not have to object. This proposition,
however, does not square with Texas law. See Dennis v. Hulse, 362 S.W.2d 308, 309 (Tex. 1962) (holding
that the mention of insurance does not always require reversal and that
the party appealing must also show that it probably caused the rendition
of an improper judgment); Meyers v. Searcy, 488 S.W.2d 509,
514-15 (Tex. Civ. App.CSan Antonio 1972, no writ) (following
Dennis). Because ACCD has waived any complaint to the alleged
mentions of insurance, and because mention of insurance is not incurable
error, we overrule this issue on appeal. Liability to
Subcontractors ACCD argues that it was error for the trial court to
submit Jury Question 3(b)(4). This question asked the jury to assess
damages for Browning=s liability to its subcontractors: AWhat sum of money, if any, paid now in cash, would
fairly and reasonably compensate Browning for its . . . liability to
subcontractors incurred by Browning to perform its work on the
Project?@ The jury answered: A$915,435.09.@ ACCD argues that it was error for the trial court to
submit this question for three reasons: 1) ACCD is not in privity with the subcontractors; 2) The subcontractors
did not assign their causes of action to Browning; and 3) Texas law does
not recognize Apass-through@ claims. Browning does not dispute the first two
arguments. Thus, the issue here is whether Texas law recognizes
pass-through claims. The submission of a theory of recovery or defense is
a question of law and is reviewable de
novo. Cont=l Cas. Co. v.
Street, 379 S.W.2d 648, 651 (Tex.
1964). In Interstate Contracting Corp. v. City of
Dallas, 320 F.3d 539, 543-44 (5th Cir. 2003), the Fifth Circuit
certified to the Texas Supreme Court the question of whether Texas
recognizes pass-through claims. Id. The court explains: In
breach of contract actions against the federal government, prime
contractors have long been permitted to present
subcontractors= claims
on a pass‑through basis against the government, even though the no‑privity rule has barred subcontractors from recovering
directly against the government. Similarly, a number of states have
permitted pass‑through claims in cases involving state government
entities. However, the specific contours and requirements for pass‑through
claims vary from jurisdiction to jurisdiction. For example, some states
permit pass‑through claims only when there is a liquidating agreement in
place that meets certain requirements, while other states permit
pass‑through claims when the prime contractor pleads the suit on behalf of
the subcontractor and has an obligation to render the recovery to the
subcontractor. The burden of proof also varies among jurisdictions.
Accordingly, in light of the absence of Texas authority on these issues
and the varied interpretations of these issues by other state courts, we
certify the following questions to the Supreme Court of Texas and the
Honorable Justices thereof. Id.
(footnotes
omitted). As the
Fifth Circuit notes, federal law as well as a significant number of states
recognize pass-through claims. Id.; see Severin v. United States, 99 Ct. Cl. 435 (1943) (holding that in a breach of contract
claim against the federal government, a prime contractor may recover
damages on behalf of its subcontractor only if the prime contractor
suffered actual damages); see also J. L. Simmons Co. v. United
States, 304 F.2d 886, 888 (Ct. Cl. 1962)
(holding that a prime contractor suffers actual damages if the prime
contractor 1) has reimbursed its subcontractor for the
subcontractor=s
damages; or 2) remains liable for such reimbursement in the future);
see also Folk Constr. Co. v. United
States, 2 Cl. Ct. 681, 685 (1983) (limiting
the application of the Severin doctrine
and holding that A[a]
prime contractor is precluded from maintaining a suit on behalf of its
subcontractor only when a contract clause or release completely exonerates
the prime contractor from liability to its
subcontractor@);
D. A. Parrish & Sons
v. County Sanitation Dist. No. 4, 344 P.2d 883, 888 (Cal. Dist. Ct.
App. 1959); Roof‑Techs Int=l, Inc.
v. State, 57
P.3d 538, 550‑53 (Kan. Ct. App. 2002); Bd. of County Comm=rs v. Cam
Constr. Co., 480
A.2d 795, 795 (Md. 1984); Kensington Corp. v. State, 253 N.W.2d
781, 783 (Mich. Ct. App. 1977); Saint Paul Dredging Co. v. State,
107 N.W.2d 717, 724 (Minn. 1961); Frank Coluccio Constr. Co. v. City
of Springfield, 779 S.W.2d 550, 551‑52 (Mo. 1989) (en banc);
Buckley & Co. v. State, 356 A.2d 56, 73‑74 (N.J. Super. Ct. Law
Div. 1975); Schiavone Constr. Co. v. Triborough
Bridge & Tunnel Auth., 209 A.D.2d 598, 599-600 (N.Y. App. Div.
1994); Metric Constructors, Inc. v. Hawker Siddeley Power Eng=g,
Inc., 468
S.E.2d 435, 438‑39 (N.C. Ct. App. 1996); Clark‑Fitzpatrick, Inc. v.
Gill, 652 A.2d 440, 449 (R.I. 1994). In United States v. Blair,
321 U.S. 730, 737-38 (1944), the Supreme Court explains the legal
reasoning behind pass-through claims: Clearly
the subcontractor could not recover this claim in a suit against the
United States, for there was no express or implied contract between him
and the Government. But it does not follow that [the contractor] is barred
from suing for this amount. [The contractor] was the only person legally
bound to perform his contract with the Government and he had the undoubted
right to recover from the Government the contract price for the tile,
terrazzo, marble and soapstone work whether that work was performed
personally or through another. This necessarily implies the right to
recover extra costs and services wrongfully demanded of [the contractor]
under the contract, regardless of whether such costs were incurred or such
services were performed personally or through a subcontractor. [The
contractor=s]
contract with the Government is thus sufficient to sustain an action for
extra costs wrongfully demanded under that
contract. Id.
(citations omitted). Courts
have also noted the equity reasons for allowing such
claims: The
holdings [allowing claims for subcontracted work] are soundly based in
reason and equity. They recognize that a direct claim by a subcontractor
against a contractee is barred by concepts of
privity as well as contractual provisions such
as here, and that if the contractor himself is barred from asserting those
claims, the contractee would be in the
extraordinary position of being responsible to no one regardless of the
nature or extent of its liabilities under its contract. No proper
justification exists for such a result. Rather, the principle adopted by
the cases is that the contractee should be
responsible to the contractor for costs or damages resulting from the
performance or breach of the contract, whether the contractor performed
the work himself or sublet it to others. Buckley, 356
A.2d at 73. Furthermore,
while no Texas case has specifically dealt with the issue of pass-through
claims, such claims are not inconsistent with Texas law. See N. Harris
County Junior Coll. Dist. v. Fleetwood Constr.
Co., 604 S.W.2d 247, 255 (Tex. Civ.
App.CHouston
[14th Dist.] 1980, writ ref=d n.r.e.) (holding that the contractor could recover for
damages related to subcontracted work); H. B. Zachry Co. v. Ceco Steel
Prods. Corp., 404 S.W.2d 113, 116, 130 (Tex. Civ. App.CEastland
1966, writ ref=d n.r.e.) (providing that the contractor has the
exclusive right and duty to assert the same claim for its subcontractor
that it would have asserted for itself had it elected to do the work done
by the subcontractor). Because
federal law and a significant number of other jurisdictions recognize
pass-through claims, because equity requires it, and because pass-through
claims are not inconsistent with Texas law, we uphold the
jury=s
finding of damages based on Browning=s
liability to its subcontractors on appeal. Estoppel Jury
Question 5 provides: AIs ACCD
estopped from relying on section 8.3.3 as a
defense to Browning=s claims
for delay damages?@ The
jury answered Ayes.@ Its
answer prevents ACCD from relying on its no-damages-for-delay clause.
ACCD
argues that Jury Question 5 submits an offensive theory of estoppel and that it was error for the trial court to
submit it. We review the submission of a theory of recovery or defense
de novo. Cont=l Cas. Co. v. Street, 379
S.W.2d 648, 651 (Tex. 1964). AEstoppel is defensive in character, and its function is to preserve
rights, and not to bring into being an independent cause of
action.@
Hermann Hosp. v. Nat=l
Standard Ins. Co., 776
S.W.2d 249, 254 (Tex. App.CHouston
[1st Dist.]1989, writ denied). Browning does not assert estoppel to bring into being an independent cause of
actionCits
cause of action is breach of contract. To the contrary, Browning asserts
estoppel to defend against
ACCD=s
no-damages-for-delay clause. Question 5 does not submit an offensive
theory of estoppel. Accordingly, it was not
error for the trial court to submit it. Added
Issue In the
estoppel section of its brief, Browning brings
up an additional argument. It argues that section 8.3.3 is not a
no-damages-for-delay clause because it reads that Browning shall receive
Ano claim
for compensation for delay.@ In
other words, Browning is arguing that the clause means that ACCD
cannot assert damages for delay against Browning. Such an argument,
if we accepted it, would provide an independent ground for affirming the
trial court=s
judgment. In other words, if section 8.3.3 is not a no-damages-for-delay
clause, Browning does not need to rely on (or defend on appeal) exceptions
(such as estoppel) to the clause. While
Browning=s
reading is clever, we find it
unconvincing. Accordingly, we overrule this issue on
appeal. Question
1 Jury
Question 1 provides: Did ACCD
fail to comply with the Contract in any of the following
respects: a.
Refusing to grant reasonable time extensions? b.
Failing to provide complete and accurate drawings to Browning; failing to
obtain building permits in a timely manner; failing or refusing to correct
design errors; or providing inaccurate or incomplete information in
response to Browning=s
requests for information? c.
Refusing to make reasonable adjustments of the Contract for time impact
and associated General Conditions cost relating to Change Orders 19
through 82? d.
Assessing liquidated damages against Browning without justification or
cause? ACCD
argues that Jury Question 1(b) violates Crown Life Insurance Co. v.
Casteel, 22 S.W.3d 378 (Tex. 2000), because two portions of
Question 1(b) are legally in question: the owner=s duty
to provide complete and accurate drawings, and the
owner=s duty
to correct design errors. Casteel provides that Awhen a
trial court submits a single broad-form liability question incorporating
multiple theories of liability, the error is harmful and a new trial is
required when the appellate court cannot determine whether the jury based
its verdict on an improperly submitted invalid theory.@
Id. at 388. Here, ACCD=s
failure to correct design errors cannot be an invalid theory of recovery
because we have already determined that ACCD owed Browning a duty to
correct such errors. Furthermore, ACCD gives us no argument or authority
to support its assertion that ACCD=s
failure to provide complete and accurate drawings was an invalid theory of
recovery. Accordingly, ACCD has waived error on this point. Tex. R. App. P.
38.1(h). Because
ACCD=s
failure to correct design errors is a valid theory of recovery, and
because ACCD fails to provide argument or authority for its contention
that failing to provide complete and accurate drawings is an invalid
theory of recovery, ACCD fails to show that Question 1(b) violates
Casteel. Accordingly, we overrule this issue on appeal.
Measure
of Damages Jury
Question 3 subpart (2) asks the jury to calculate damages, if any, for
Aadditional
home office overhead costs incurred by Browning to perform its work on the
Project.@ The
question instructs the jury that damages for home office overhead costs
are to be calculated Aby the
daily rate of overhead allocable to the Contract and multiplying it by the
number of days the job was extended.@[3] ACCD argues that the submission of this instruction
was error because Texas law does not recognize the Eichleay method of calculating damages. Whether the
trial court applied the improper measure of damages is a question of law
subject to a de novo review.
Elias v. Mr. Yamaha, Inc., 33 S.W.3d 54, 60 (Tex.
App.CEl Paso 2000, no pet.). ACCD cites Chilton Insurance Co. v. Pate &
Pate Enterprises, Inc., 930 S.W.2d 877, 892 (Tex. App.CSan Antonio 1996, writ denied) for the proposition
that Texas law does not recognize the Eichleay
method of calculating damages. Chilton, however, expressly declines
to decide that issue. See id. (A[W]e find it unnecessary to decide the propriety of
using the Eichleay formula or any of its
modified versions to calculate overhead damages.@). Thus, ACCD has failed to present authority for its
argument. Because ACCD has failed to present authority for its
contention that Texas law does not recognize the Eichleay method of calculating damages, it has waived
this issue. Tex. R. App. P.
38.1(h). Accordingly, we overrule this issue on
appeal. Causation In Jury Question 1(b), the jury found that ACCD
breached the contract by failing to provide complete and accurate
drawings; failing to obtain building permits in a timely manner; failing
or refusing to correct design errors; or providing inaccurate or
incomplete information in response to Browning=s requests for information. The jury further found
that the following delay damages resulted from that breach:
Additional job site costs:
$716,622.28 Additional home overhead costs:
$293,656.06 Additional management costs:
$260,715.22 Liability to subcontractors:
$915,435.09 Additional work and changed work proposals:
$351,821.61 Change negotiation support costs:
$86,552.25 A.
Legal Sufficiency ACCD argues that the evidence is legally insufficient
to support these damages because Browning failed to provide any evidence
showing that its damages were caused by ACCD=s alleged breach. An appellant attacking the legal sufficiency of an
adverse finding on which he did not have the burden of proof must
demonstrate that there is no evidence to support the adverse finding.
Croucher v. Croucher, 660 S.W.2d 55, 58 (Tex. 1983). The
reviewing court must consider all evidence in a light most favorable to
the party in whose favor the verdict has been rendered and indulge every
reasonable inference from the evidence in such party=s favor. Harbin v. Seale, 461 S.W.2d 591, 592
(Tex. 1970). If more than a
scintilla of evidence exists to support the finding, the no evidence
challenge fails. Formosa Plastics Corp. USA v. Presidio
Eng=rs and Contractors, Inc., 960 S.W.2d 41, 48 (Tex.
1998). At trial, Browning=s critical path and damages expert, Phil Apprill, testified extensively about design defects
and incomplete specifications that caused Browning delay. These included
defects in roof geometry, ceiling design, and window installation plans,
as well as incomplete specifications for pier caps, beams, electrical
services, and draft stops. Other witnesses testified in further detail
about these same problems and how they caused Browning delay. These
witnesses included Robert Browning, Browning=s project manager, Bill Johnson, Browning=s operations supervisor, and John Wall, a structural
engineer. Apprill also testified to how these
breaches caused delay, as well as how much delay they caused and the
monetary value of that delay. Thus, Browning presented more than a
scintilla of evidence that ACCD=s breaches caused delay. ACCD argues that Texas law requires that the
contractor demonstrate a factual connection between each separate
delay damage he has sustained and the actions of the owner. The cases ACCD
cites, however, fail to establish such a requirement. City of Beaumont
v. Excavators & Contractors, 870 S.W.2d 123, 140-41 (Tex.
App.CBeaumont 1993, writ denied), overturns a
jury=s award of delay damages where there was no evidence
that defendant caused plaintiff=s delay damages. And in City of Houston v. R. F.
Ball Construction Co., 570 S.W.2d 75, 78 (Tex. Civ. App.CHouston [14th Dist.] 1978, writ ref=d n.r.e.), the plaintiff
could not establish he was entitled to delay damages.
Because there is more than a scintilla of evidence to
support the finding that ACCD=s breaches caused delay, and because ACCD has
provided no authority for its contention that Texas law requires that the
contractor demonstrate a factual connection between each separate
delay damage he has sustained and the actions of the owner, we overrule
this issue on appeal. B.
Factual Sufficiency ACCD also argues that the evidence is factually
insufficient to support these damages because Browning failed to provide
any evidence showing that its damages were caused by
ACCD=s alleged breach. A party attacking the factual sufficiency of an
adverse finding on an issue on which the other party had the burden of
proof must demonstrate that there is insufficient evidence to support the
adverse finding. Hickey v. Couchman, 797
S.W.2d 103, 109 (Tex. App.CCorpus Christi 1990, writ denied). In reviewing an
insufficiency of the evidence challenge, the court must first consider,
weigh, and examine all of the evidence which supports and which is
contrary to the jury=s determination. Plas-Tex, Inc. v. U.S. Steel Corp., 772
S.W.2d 442, 445 (Tex. 1989) (per curiam). Having done so, the court should
set aside the verdict only if the evidence that supports the jury finding
is so weak as to be clearly wrong and manifestly unjust. Cain v.
Bain, 709 S.W.2d 175, 176 (Tex. 1986) (per curiam). Here, ACCD fails to point out any evidence contrary
to the jury=s determination and as such has failed to adequately
brief this issue. Tex. R. App. P.
38.1(h). Even if ACCD had adequately briefed this issue, however,
upon our review of the record as summarized above, we do not find the
evidence so weak as to be clearly wrong and manifestly unjust.
Accordingly, we overrule this issue on
appeal. Modification of
Contract In Jury Question 6, the jury found that ACCD and
Browning modified the contract. This finding prevents ACCD from relying on
its no-damages-for-delay clause as a defense to Browning=s claims. ACCD argues that the evidence is legally
and factually insufficient to support the jury=s finding because Browning gave ACCD no new
consideration for the modification. We do not need to decide this issue, however, because
ACCD has failed to challenge the legal and factual sufficiency of the
evidence supporting the jury=s findings on four other questions that
prevent ACCD from relying on its no-damages-for-delay clause. Thus, even
if we were to find that the evidence of consideration is legally or
factually insufficient, there remain four unchallenged jury findings
preventing ACCD from relying on its no-damages-for-delay clause. Because
there are four unchallenged jury findings that prevent ACCD from relying
on its no-damages-for-delay clause, we need not decide whether the
evidence of consideration is legally or factually sufficient to support
the jury=s finding.
Design
Error ACCD next argues that there is not legally or
factually sufficient evidence of design error because Browning provided no
expert testimony on the standard of care of an architect. ACCD cites
several cases for the proposition that a licensed architect must testify
regarding the work of another licensed architect, and a directed verdict
is proper absent this type of expertise being provided. ACCD fails to show
us, however, why such testimony is necessary in a breach-of-contract
case. Because ACCD has failed to show how its statement of
law applies to this case, it has waived this issue. Tex. R. App. P. 38.1(h). We,
therefore, overrule it on appeal. Motion for New
Trial ACCD argues that the trial court abused its
discretion by denying ACCD=s motion for new trial. We review a trial
court=s order denying a motion for new trial under an abuse
of discretion standard. Washington v. McMillan, 898 S.W.2d 392, 394
(Tex. App.CSan Antonio, 1995, no writ). A trial court abuses its discretion if it acts in an
arbitrary or unreasonable manner without reference to any guiding rules or
principles. Downer v. Aquamarine Operators, Inc., 701 S.W.2d 238,
241-42 (Tex. 1985). ACCD argues that the trial court abused its
discretion by denying ACCD=s motion for new trial because the evidence is
factually insufficient to support the jury=s finding in Question 1(c). Question 1(c) provides:
ADid ACCD fail to comply with the Contract [by]
[r]efusing to make reasonable adjustments of the
Contract for time impact and associated General Conditions cost relating
to Change Orders 19 through 82?@ The jury answered Ayes@ but found no damages. Thus, with respect to Question
1(c), the jury found that ACCD owed Browning
nothing. ACCD fails to explain how a new trial could have
resulted in a more favorable finding for ACCD. We do not see how the trial
court could have abused its discretion in failing to grant
ACCD=s motion. Thus, we overrule this issue on
appeal. Waiver In Jury Question 4, the jury found that ACCD waived
its right to rely on its no-damages-for-delay clause as a defense to
Browning=s claims for delay damages. ACCD argues that the
evidence of waiver is legally and factually insufficient to support the
jury=s finding. Again, we do not need to decide this issue, because
ACCD has failed to challenge the legal and factual sufficiency of the
evidence supporting the jury=s findings on four other questions that
prevent ACCD from relying on its no-damages-for-delay clause. Thus, even
if we were to find that the evidence of waiver is legally or factually
insufficient, there remain four unchallenged jury findings preventing ACCD
from relying on its no-damages-for-delay clause. Because there are four
unchallenged jury findings that prevent ACCD from relying on its
no-damages-for-delay clause, we need not decide whether the evidence of
waiver is legally or factually sufficient to support the jury=s finding. Breach At trial, the jury found that ACCD breached the
contract in four ways: 1) by refusing to grant reasonable time extensions;
2) by failing to provide complete and accurate drawings to Browning;
failing to obtain building permits in a timely manner; failing or refusing
to correct design errors; or providing inaccurate or incomplete
information in response to Browning=s requests for information; 3) by refusing to make
reasonable adjustments of the contract for time impact and associated
General Conditions cost relating to Change Orders 19 through 82; and 4) by
assessing liquidated damages against Browning without justification or
cause. ACCD argues that the evidence is legally and factually insufficient
to support the jury=s findings in all four of these breach questions. We
review legal and factual sufficiency issues under the standards set out
above. Question
1(a) provides: ADid ACCD fail to comply with the Contract [by]
[r]efusing to grant reasonable time
extensions?@ The jury answered Ayes.@ ACCD argues that the evidence is legally and
factually insufficient to support this finding. The record reflects,
however, that Phil Apprill, Browning=s critical path and damages expert, testified that
there were 101 days of delay in Phase A of construction and 296 days of
delay in Phase B. Apprill further testified that
these delays were beyond Browning=s control and that ACCD should therefore have granted
Browning reasonable time extensions as provided by the contract. Richard
Morales, the manager of the joint venture that designed the project,
agreed that the contract required that Browning be given reasonable time
extensions, and testified that ACCD never considered these time
extensions, despite numerous requests. This is more than a scintilla of
evidence that ACCD failed to comply with the contract by refusing to grant
reasonable time extensions. Furthermore, the evidence is not so weak as to
be clearly wrong and manifestly unjust. Accordingly, we overrule this
issue on appeal. Question 1(b) provides: ADid ACCD fail to comply with the Contract [by]
[f]ailing to provide complete and accurate drawings to Browning; failing
to obtain building permits in a timely manner; failing or refusing to
correct design errors; or providing inaccurate or incomplete information
in response to Browning=s requests for information?@ The jury answered Ayes.@ ACCD argues that the evidence that ACCD provided
inaccurate or incomplete information in response to Browning=s requests is legally and factually insufficient to
support the jury=s finding. The record reflects, however, that Robert
Browning, Browning=s project manager, testified to several instances
where Browning submitted requests for information and received inaccurate
or incomplete responses. One example was when Browning discovered that the
original design failed to provide enough structural support for a certain
wall to withstand wind loads. Browning submitted three separate requests
for information on that issue, never got a complete response, and
eventually had to come up with a new design on its own. This is more than
a scintilla of evidence that ACCD failed to comply with the contract by
providing inaccurate or incomplete information in response to
Browning=s requests for information. Furthermore, the evidence
is not so weak as to be clearly wrong or manifestly unjust. Accordingly,
we overrule this issue on appeal. Because the evidence is legally and factually
sufficient to support the jury=s findings in Questions 1(a) and 1(b), we overrule
this issue on appeal. Remaining
Issues ACCD has brought up several other issues in its
brief.[4]
Because, however, it fails to present argument or authority for these
issues, these issues are waived. Tex. R. App. P. 38.1(h).[5]
We decline, therefore, to address them on appeal. Prompt Pay
Act The Prompt Pay Act provides that a contractor that
supplies goods or services to a political subdivision whose governing body
meets only once a month or less is entitled to recover interest on
payments that are forty-six days overdue. Tex. Gov=t Code Ann. '' 2251.021, 2251.025, 2251.026 (Vernon Supp. 2003). A
party who prevails on a Prompt Pay Act claim is entitled to reasonable
attorney fees. Id. ' 2251.043 (Vernon 2000). At trial, the jury found that ACCD did not violate
the Prompt Pay Act. Following the verdict, Browning filed a motion for
JNOV, asking the trial court to disregard the jury=s finding and render judgment for Browning. The trial
court denied the motion. In its cross-appeal, Browning argues that the trial
court erred in denying its motion because the jury findings in Questions
1(d) and 14 are in conflict. We review the denial of a motion for JNOV under a
legal sufficiency standard, meaning we review the evidence in the light
most favorable to the jury findings, considering only the evidence and
inferences that support them and disregarding all evidence and inferences
to the contrary. Quaker Petroleum Chems. Co.
v. Waldrop, 75 S.W.3d 549, 553 (Tex. App.CSan Antonio 2002, no pet.). If there is more than a
scintilla of evidence to support the findings, the motion for JNOV was
properly denied. Id. Only if there is no evidence to support the
jury=s findings must we examine the entire record to see
if the contrary position is established as a matter of law.
Id. In its reply brief, ACCD argues that the trial court
did not err in denying Browning=s motion for JNOV because the jury findings in
Questions 1(d) and 14 are not in
conflict. In reviewing jury findings for conflict, the
threshold inquiry is whether the findings implicate the same material
fact. Bender v. S. Pac. Transp. Co., 600
S.W.2d 257, 260 (Tex. 1980). A court may not strike jury answers based on
conflict if any reasonable basis exists upon which the conflict can be
reconciled. Luna v. S. Pac. Transp. Co.,
724 S.W.2d 383, 384 (Tex. 1987). The reviewing court must reconcile
apparent conflicts in the jury=s findings, if reasonably possible, considering the
pleadings and evidence, the manner of submission, and the other findings
considered as a whole. Bender, 600 S.W.2d at 260. When the issues
submitted have more than one reasonable construction, the reviewing court
will generally adopt the construction that avoids a conflict in the
answers. Id. The test for determining whether an irreconcilable
conflict between issues exists is whether one finding alone requires
judgment in the plaintiff=s favor and the other finding taken alone requires
judgment in the defendant=s favor. Farmland Mut.
Ins. Co. v. Alvarez , 803 S.W.2d 841, 847 (Tex. AppCCorpus Christi 1991, no writ); Grice v.
Hennessy, 327 S.W.2d 629, 633 (Tex. Civ.
App.CSan Antonio 1959, no writ). Or, as one court phrased
it: ATo determine whether there is reversible error, the
appellate court must only decide whether the conflict is such that one
answer would establish a cause of action or defense, while the other would
destroy it.@ Sterling Trust Co. v. Adderley, 119 S.W.3d 312, 320 (Tex.
App.CForth Worth 2003, pet. filed) (citing Little Rock
Furniture Mfg. Co. v. Dunn, 148 Tex. 197, 222 S.W.2d 985, 991
(1949)). Question 1(d) asks the jury: ADid ACCD fail to comply with the Contract [by]
assessing liquidated damages against Browning without justification or
cause?@ The jury answered Ayes@ and awarded Browning $376,000 in damages. Question
14 asks the jury: ADid ACCD allow any payments owed to Browning under
the Contract to become overdue?@ The jury answered Ano.@ Browning argues that because the jury found in
Question 1(d) that ACCD wrongfully withheld payments from Browning, and
because it is undisputed that these payments were more than forty-six days
overdue, the jury=s finding in Question 14 that ACCD did not allow any
payments owed to Browning to become overdue conflicts with its finding in
Question 1(d).[6]
The jury=s finding that ACCD wrongfully withheld payments,
Browning argues, was a specific finding that should control the
general finding that ACCD did not allow any payments owed to
Browning to become overdue. Therefore, Browning argues, we should reverse
and render judgment for Browning, awarding it interest on the wrongfully
withheld payments and stipulated attorneys= fees of
$733,684.74. Neither Question 14 nor Question 1(d) taken alone,
however, requires judgment in one party=s favor while the other finding taken alone requires
judgment in the other party=s favor. Farmland Mut., 803 S.W.2d at 847. Question 1(d) is a breach
of contract question. Question 14 is a Prompt Pay Act question. The two
questions go to different causes of action. Thus, the conflict is not such
that one answer would establish a cause of action or defense while the
other would destroy it. Little Rock, 222 S.W.2d at 991; Sterling
Trust Co., 119 S.W.3d at 320. Because Browning fails to meet the test for
conflicting jury findings, we overrule its
cross-issue. Conclusion We affirm the judgment of the trial
court. Karen Angelini,
Justice [1]Jury Question 1(b) provides: Did ACCD fail to comply with the Contract in any
of the following respects: Failing to provide complete and accurate
drawings to Browning; failing to obtain building permits in a timely
manner; failing or refusing to correct design errors; or providing
inaccurate or incomplete information in response to Browning=s request for information? [2]The
first instance is in Browning=s
opening argument, where counsel uses the words Aerror
or omission@:
There is evidence that
you will see in the form of written evidence that the architect team, the
different members of the architect team, wouldChad
sent a memo to the other sayingCon
these change order formsCthere
was a change order form, the evidence will show, that Mr. Fernandez, who
is the ACCD representative on the project, created a form which would say
one of the items would be change to work, would be omission or error in
the documents or words to that effect, and you will see a memo within the
architect team where it says to the other members, Don=t
ever check error or omission. Regardless of what the issue was,
this was just a general agreement, Don=t
ever check that. The
second instance is where Browning asks the following question of an
architect: ADo
you know why your carrier, your E and O carrier is paying a lawyer to
represent you?@ [3]
The jury assessed $293,656.06 in damages against Browning for home office
overhead costs incurred by Browning. [4]
These issues are: 1) ACCD=s
argument that Jury Question 1should have referred the jury to specific
contract provisions at issue; 2) ACCD=s
argument that the jury charge improperly submitted a Atotal
cost@
theory of damages; 3) ACCD=s
argument that the jury charge improperly allowed the plaintiff to recover
attorney fees Browning incurred when it negotiated a settlement with its
subcontractors; 4) ACCD=s
argument that the evidence is legally and factually insufficient to
support the jury=s
findings in Jury Questions 1(c) and 1(d); and 5) ACCD=s
argument that the evidence of overhead costs is legally and factually
insufficient because Browning presented no evidence that it was unable to
take on additional work during the delay. [5]
Even if ACCD had presented argument and authority for these issues,
however, we do not believe that any of these issues would have succeeded
on appeal. [6]
Browning argues that the jury found in Question 1(d) that ACCD wrongfully
withheld payments. Although Question 1(d) seems to be about liquidated
damages, not payments, Browning shows that when ACCD assessed liquidated
damages without cause, it did not require Browning to pay those damages to
ACCD. Rather, ACCD offset the payments it owed Browning by those amounts.
Thus, the liquidated damages ACCD assessed against Browning were, in fact,
payments ACCD owed to
Browning. | |