Send this document to a
colleague |
Close
This Window | |||||||||||||||||||
|
Opinion Issued April
13, 2006
In The Court
of Appeals For The First
District of Texas
NO. 01-04-01293-CV
FONDREN CONSTRUCTION CO., INC. AND ROBERT G.
LUBKEMAN, Appellants V. BRIARCLIFF HOUSING DEVELOPMENT ASSOCIATES, INC.,
DPMC-BRIARCLIFF, L.P., AND JOHN DEERE COMPANY,
Appellees
On Appeal from the 165th District
Court Harris County, Texas Trial Court Cause No.
2000-53187
O P I N I
O N
Fondren Construction Co., Inc. and Robert Lubkeman (collectively
“Fondren”) appeal from a summary judgment rendered on behalf of appellee
John Deere Company (“John Deere”), and a motion for judgment rendered in
favor of appellees Briarcliff Housing Development Associates, Inc.
(“BHDA”) and DPMC-Briarcliff, L.P. (“DPMC”) during a bench trial. Fondren sued for breach of
contract, unjust enrichment, foreclosure of lien interest, fraud and fraud
in the inducement, negligent misrepresentation, and a right to recover on
a payment bond, alleging it was not paid in full for construction
subcontracting work performed on the Briarcliff property. On appeal, Fondren contends the
trial court erred in granting summary judgment in favor of John Deere
because it presented improper summary judgment evidence and the bond it
relied on fails to meet the requirements of the Texas Property Code. Fondren further contends the trial
court erred in granting judgment in favor of BHDA and DPMC at the close of
its case because the evidence introduced during the bench trial thus far
proved Fondren’s claims. We
affirm. BACKGROUND
In January 1999, Westbrook Construction contracted with BHDA to
perform services at the Briarcliff Apartments. John Deere, acting as surety, filed
a payment bond covering the work to be performed under the contract. Around the same time, Lubkeman
contracted with Westbrook, subject to Westbrook’s contract with BHDA, to
perform supervisory work in an individual capacity and to perform
contracting work in his capacity as owner of Fondren Construction
Company. Westbrook paid
Fondren initially. At some
point, Westbrook stopped work, and another contractor completed the work
at Briarcliff. At the time,
Westbrook owed additional amounts to Fondren. After Westbrook stopped work,
Fondren alleges BHDA and DPMC promised full payment of the amounts due
under the contracts with Westbrook.
Fondren further contends this promise encouraged it to continue
work on the property for BHDA and DPMC. In February 2000, Lubkeman
filed liens against the Briarcliff property on behalf of himself and
Fondren. Lubkeman testified
that none of the work he performed for which he demands payment occurred
after he filed the liens. In
October 2000, Lubkeman sued BHDA and Westbrook. In August 2003, he amended the
petition, removing Westbrook as a party to the suit, adding DPMC and John
Deere as parties, and adding a cause of action on the payment bond.[1] John Deere moved for summary
judgment, which the trial court granted. The case proceeded to a bench
trial. After Fondren rested,
BHDA and DPMC moved for judgment, which the trial court also granted. Fondren appeals from both
decisions. THE
PAYMENT BOND
Fondren contends that the payment bond is not a valid defense to
either John Deere’s motion for summary judgment or DPMC and BHDA’s motion
for judgment because the bond fails to comply with the requirements of the
Property Code. Because the
validity of the payment bond affects the merit of Fondren’s claims against
all of the appellees in this case, we address Fondren’s attacks as to the
bond first. See Tex. Prop. Code Ann. § 53.201 (Vernon Supp. 2005) (“if a valid
bond is filed, a claimant may not file suit against the owner or the
owner’s property”); see also Laughlin Envtl., Inc. v. Premier Towers,
L.P., 126 S.W.3d 668, 675 (Tex. App.—Houston [14th Dist.] 2004, no
pet.) (explaining how compliance with statutory bond requirements affects
underlying lien claims).
First, Fondren argues John Deere’s bond does not prominently
display contact information as Texas Property Code section 53.202(6)
requires. See Tex Prop. Code Ann. § 53.202(6)
(Vernon Supp. 2005). John
Deere issued the bond in this case in January 1999. The Legislature added subsection 6
to the statute in May 2001, and it did not take effect until September 1,
2001. See Act of May
15, 2001, 77th Leg., R.S., ch. 380, § 5, 7, 2001 Tex. Gen. Laws 706,
707–08 (amended nonsubstantively 2005) (current version at Tex. Prop. Code Ann. § 53.202(6)
(Vernon Supp. 2005)). The
statutory contact information requirements did not exist when John Deere
filed the bond; thus, no fact issue exists regarding John Deere’s
compliance with subsection 6. Second, Fondren relies on
section 53.202(1) of the Property Code, which requires that the penal sum
of the bond be at least equal to the original contract amount. See
Tex. Prop. Code Ann. §
53.202(1). Because the penal
sum sets the financial limits of the surety’s obligations, it is the most
material aspect of a payment bond.
Laughlin, 126 S.W.3d at 674 (citing
Sherwin-Williams Co. v. Am. Indem. Co., 504 S.W.2d 400, 402 (Tex.
1973)). Here, Fondren sued
John Deere on a payment bond it executed on January 11, 1999. The bond covers the contract
entered into between Westbrook and Briarcliff on January 12, 1999. The original amount of the contract
between Westbrook and Briarcliff is $4,224,485.00, and the amount of the
payment bond issued by John Deere is $4,224,485.00—exactly equal to the
amount of the contract. The
contract and the bond are evidence that the bond is in a penal sum equal
to the total of the original contract, and Fondren did not offer any
controverting evidence. Thus,
no fact issue exists regarding compliance with subsection 1 of the
statute. We hold that the
payment bond complied with the Property Code’s requirement with respect to
section 53.202(1). SUMMARY
JUDGMENT As its sole ground for summary
judgment, John Deere contends that Fondren cannot recover on the valid
payment bond because Fondren failed to bring suit within the one year
allowed by the Property Code.
See Tex. Prop. Code
Ann. § 53.208 (Vernon 1995)
(setting time limit for suit on bond). Fondren responds that the
affidavit testimony of David Styers, a vice president for John Deere, is
improper summary judgment evidence, and that the bond does not cover the
work at issue in this case.
Fondren re-urges these arguments on appeal. A. Standard of
Review We review the trial court’s
ruling on a summary judgment motion de novo. See Provident Life &
Accident Ins. Co. v. Knott, 128 S.W.3d 211, 215 (Tex. 2003). We view the evidence in the light
most favorable to the non-movant, making all reasonable inferences and
resolving all doubts in the non-movant’s favor. Sw. Elec. Power Co. v.
Grant, 73 S.W.3d 211, 215 (Tex. 2002). The movant for a traditional
summary judgment has the burden of showing that there is no genuine issue
of material fact and that it is entitled to judgment as a matter of
law. Tex. R. Civ. P. 166a(c); Haase v.
Glazner, 62 S.W.3d 795, 797 (Tex. 2001). A defendant seeking summary judgment must negate as a
matter of law at least one element of each of the plaintiff’s theories of
recovery or plead and prove as a matter of law each element of an
affirmative defense. Johnson County Sheriff's Posse
v. Endsley, 926 S.W.2d 284, 285 (Tex. 1996). If the movant can show it is
entitled to judgment as a matter of law, the burden shifts to the
non-movant to present evidence raising a fact issue to defeat the motion
for summary judgment.
Flores v. N. Am. Techs. Group, Inc., 176 S.W.3d 442, 446
(Tex. App.—Houston [1st Dist.] 2004, pet. denied). B. Affidavit of Interested
Party
Fondren contends Styers’s affidavit is improper summary judgment
evidence because Styers is an interested witness, and his affidavit
contains conclusory statements.
A trial court may grant summary judgment based on the
uncontroverted testimony of an interested witness if the testimony is
“clear, positive and direct, otherwise credible and free from
contradictions and inconsistencies, and could have been readily
controverted.” Tex. R. Civ. P. 166a(c). Styers avers in the affidavit
that he is the vice president of the company formerly known as John Deere,
and is the custodian of the records pertaining to this case. He further avers that the payment
bond and contract offered as summary judgment evidence are true and
correct copies of the bond and contract in issue in this case. Fondren offered no argument or
summary judgment evidence to suggest this testimony is not clear,
positive, direct, free from contradictions, and readily
controvertible. See Casso
v. Brand,
776 S.W.2d 551, 558 (Tex. 1989) (“could have been readily controverted” means
“testimony at issue can by its nature be effectively countered by opposing
evidence”); Larson v. Family Violence & Sexual Assault Prevention
Ctr. of S. Tex., 64
S.W.3d 506, 513 (Tex.
App.—Corpus Christi 2001, pet. denied) (holding affidavit attesting to
authenticity of letter was proper summary judgment
evidence). If Fondren had evidence to
contradict Styers’s claims regarding his position at John Deere, or the
accuracy of the bond and contract, then our summary judgment rules place
the burden on Fondren to come forth with such evidence once John Deere
moved for a summary judgment.
Furthermore, Fondren fails to demonstrate how any of the factual
statements made in Styers’s affidavit are conclusory. We thus hold that Fondren fails to
raise a fact issue with regard to Styers’s
affidavit. B. Failure to Bring Suit Within the
Limitations Period John Deere contends Fondren’s
suit against it is barred by the existence of a valid payment bond and its
corresponding statute of limitations. An original contractor who has a
written contract with the owner may furnish a bond for the benefit of
claimants, such as subcontractors who are not paid for their work. Tex. Prop. Code Ann. §
53.201(a). The bond protects anyone with a
claim perfected in a manner prescribed for fixing a lien under subchapter
C of the Code. See Act
of May 24, 1983, 68th Leg., R.S., ch. 576, § 1, 1983 Tex. Gen. Laws 3475,
3552 (amended 1999) (current version at Tex. Prop. Code Ann. §
53.205(a)(1) (Vernon Supp. 2005)).
Section 53.052 allows a claimant to perfect a claim by filing an
affidavit with the county clerk no later than the fifteenth day of the
fourth month after the day on which the indebtedness accrues. Tex. Prop. Code Ann. § 53.052(a)
(Vernon Supp. 2005).
Indebtedness to a subcontractor accrues on the last day of the last
month in which the labor was performed or material furnished. Id. § 53.053(c). A claimant may sue the surety on a
bond “if his claim remains unpaid for 60 days after the claimant perfects
the claim.” Tex. Prop. Code Ann. § 53.208(a)
(Vernon 1995). “If the bond
is recorded at the time the lien is filed, the claimant must sue on the
bond within one year following perfection of his claim.” Id. § 53.208(d).
Here, Fondren failed to sue on the bond within the statutorily
allowed period. Fondren
alleges that the work performed at Briarcliff ended in December 1999, and
thus the indebtedness accrued on December 31, 1999. See Tex. Prop. Code Ann. § 53.053(c)
(Vernon Supp. 2005). Fondren
perfected its claim by filing affidavits with the county clerk on February
24, 2000, within the time allowed for perfection under the statute. See id. § 53.052(a). John Deere recorded its bond on
January 13, 1999; thus, Fondren had one year from February 24, 2000 to
file suit on the bond. Tex. Prop. Code Ann. § 53.208(d)
(Vernon 1995). Fondren did
not sue on the bond, or add John Deere as a party to the suit, until
August 18, 2003, well after the time limit. We therefore hold that the suit
against John Deere is barred by the statute of limitations. Compare Sherwin-Williams,
504 S.W.2d at 401 (joinder of surety after time limit set by statute would
have been untimely if statute applied), with Mathews Constr. Co. v.
Jasper Hous. Constr. Co., 528 S.W.2d 323, 328 (Tex. Civ. App.—Beaumont
1975, writ ref’d n.r.e.) (where amended complaint filed after limitations
period added action on bond, but surety had been named in original
pleading filed within limitations period, suit on bond was timely). Fondren argues that appellees
conspired to withhold the existence of the bond despite his repeated
request that they produce it.
However, the bond was on file in the county records beginning
January 13, 1999, before Fondren filed its liens. “An instrument that is properly
recorded in the proper county is notice to all persons of the existence of
the instrument.” See
Act of May 24, 1983, 68th Leg., R.S., ch. 576, § 1, 1983 Tex. Gen.
Laws 3475, 3495–96 (amended 2003) (current version at Tex. Prop. Code Ann. § 13.002
(Vernon 2004)). Thus, the
appellees’ failure to produce the bond when requested does not affect the
applicability of the bond to this case. Fondren’s failure to add John Deere
as a party within one year of perfecting its claim bars its suit against
John Deere. C. Applicability of Bond to This
Case
Fondren’s final argument against summary judgment is that a fact
issue remains concerning whether the bond attached to John Deere’s motion
for summary judgment applies to Fondren’s claims in this case. In its fourth amended petition,
Fondren added John Deere as a defendant, and added a cause of action
entitled “Suit on Bond.”
Fondren asserts that “[r]ecently Lubkeman learned that John Deere
provided a bond for the subject property. . . . Fondren and Lubkeman therefore
bring this suit against John Deere and seek payment as required under the
terms of the bond.”
The bond covers work done
pursuant to a January 12, 1999 contract between Westbrook and
Briarcliff. Fondren claims
the work for which it was not paid began during 1998, and therefore the
burden is on John Deere to demonstrate the applicability of the bond to
this case. First, though
Fondren asserted, both in its petition and at oral argument, that the work
for which it demands payment began in 1998, it failed to present any
summary judgment evidence to that effect. The only contract in the record
for work to be performed by Fondren for Westbrook is a contract dated
January 13, 1999, which is made subject to the contract between Westbrook
and Briarcliff entered into on January 12, 1999, for which John Deere
filed a bond. There is no
evidence to suggest that Fondren performed any work for Briarcliff prior
to 1999. Even if the bond did
not cover the work for which Fondren is demanding payment, then Fondren
could not recover on the bond, and John Deere would not be a proper party
to this suit because John Deere would not be a party to any contracts for
work performed by Fondren before the date of the bond. Fondren did not sue John Deere for
anything other than the bond for which John Deere is the surety. We therefore hold this argument
fails to raise a fact issue as to Fondren’s claim for payment against John
Deere. Accordingly, we hold the trial
court did not err in granting summary judgment in favor of John
Deere. MOTION
FOR JUDGMENT
At the close of Fondren’s case, BHDA and DPMC moved for a “directed
verdict” on the grounds that Fondren’s suit is barred by the Property Code
because a valid bond was on file for the work at issue, no evidence
established any of the alleged misrepresentations were made by either
defendant, and no evidence established intent to commit fraud. The trial court granted the
motion. A. Standard of
Review
We construe BHDA and DPMC’s motion as a motion for judgment rather
than a directed verdict,
because they brought it after the plaintiffs rested in a bench trial. See Qantel Bus. Sys., Inc. v.
Custom Controls Co., 761 S.W.2d 302, 303 (Tex. 1988); Ashcreek
Homeowner’s Ass’n, Inc. v. Smith, 902 S.W.2d 586, 587 n.1 (Tex.
App.—Houston [1st Dist.] 1995, no writ). As the arbiter of factual and
legal issues, the judge in a nonjury trial has the authority to rule on
both the legal and factual sufficiency of the plaintiff’s evidence on the
defendant’s motion for judgment, after hearing only the plaintiff’s evidence.
Qantel, 761 S.W.2d at
304. On appeal, the legal and
factual sufficiency of the evidence to support the judgment can be
challenged as in any other nonjury case. Ashcreek, 902 S.W.2d at 587.
When we review legal
sufficiency, we review the evidence in a light that tends to support the
finding of the disputed facts and disregard all evidence and inferences to
the contrary. Lee Lewis
Constr., Inc. v. Harrison, 70 S.W.3d 778, 782 (Tex. 2001). When we review factual
sufficiency, we conduct a neutral review of all the evidence. Cain v. Bain, 709 S.W.2d
175, 176 (Tex. 1986). We
reverse for factual insufficiency only if the ruling is so against the
great weight and preponderance of the evidence as to be manifestly
erroneous or unjust. Minucci v. Sogevalor, S.A., 14 S.W.3d 790, 794
(Tex. App.—Houston [1st Dist.] 2000, no pet.). B. Effect of Bond on Fondren’s
Claims As owners of the property on
which the work at issue was performed, BHDA and DPMC contend the existence
of a valid payment bond covering the work in question bars Fondren’s
claims against them. If a
payment bond meets statutory requirements, a claimant may not file lien
claims against a property owner or seek foreclosure of the lien on the
owner’s property. See
Tex. Prop. Code Ann. § 53.201(b) (Vernon Supp.
2005) (“if a valid bond is filed, a claimant may not file suit against the
owner or the owner’s property”); Laughlin, 126 S.W.3d at 671. “A payment bond, executed by an original contractor, is substituted
for whatever other relief might be obtained by subcontractors and those
furnishing materials and labor against the owner and
his property.” Sentry Ins. Co. v. Radcliff
Materials of Tex., Inc., 687 S.W.2d 437, 440 (Tex. App.—Houston [14th
Dist.] 1985, no writ) (citing Fid. & Deposit Co. of Md. v.
Felker, 469 S.W.2d 389 (Tex. 1971)). The bond in this case satisfies
the requirements of the statute.
The bond was recorded in January 1999 pursuant to a contract
between Westbrook, the general contractor, and BHDA, the property
owner. Lubkeman testified
that the BHDA project came up in 1999, that he entered into contracts with
Westbrook to do work at BHDA’s property, and that all the work for which
he claims he was not paid was performed prior to the filing of the liens
in Februrary 2000. He further
testified that he “imagined” the bond in this case covers the work he
performed on BHDA’s property.
See Tex. Prop.
Code Ann. §
53.201(b). Though Fondren
claims the bond was kept a secret, it had been recorded in the public
records before Fondren filed its lien on the property—thus, Fondren had
constructive notice of its existence. Under the Property Code, the bond
substituted for any other relief Fondren might seek against the property
owners. Id. Accordingly, we hold that the
trial court did not err in finding that the bond barred Fondren’s claims
against the property owners BHDA and DPMC. In addition, the trial court
properly entered judgment for BHDA and DPMC because Fondren failed to
establish its negligent misrepresentation, fraud, and unjust enrichment
claims against them. Lubkeman
testified that Larry Hill, the owner of Westbrook, asked Fondren to
continue work on the Briarcliff project despite Westbrook’s problems. Lubkeman testified that after
Westbrook left the job, he continued working for HRI, a DPMC-related
entity. He testified that
after HRI left, Davis Penn, the president of DPMC, told Fondren and some
other subcontractors that “all bills would be paid” if they continued to
work at Briarcliff. Lubkeman
testified that he would not have continued working if he had not been
given such assurances.
Lubkeman, however, admitted that Fondren received full payment from
DPMC and BHDA for the work he performed after Westbrook’s departure,
including while working for HRI.
Fondren’s contention is that Penn’s assurance amounted to a promise
to pay amounts Westbrook owed to it, and that it would not have continued
working on the Briarcliff project if not for such
assurances. A person commits fraud by (1)
making a false, material misrepresentation (2) that the person either
knows to be false or asserts recklessly without knowledge of its truth (3)
with the intent that the misrepresentation be acted upon, (4) and the
person to whom the misrepresentation is made acts in reliance upon it (5)
and is injured as a result.
Formosa Plastics Corp. USA v. Presidio Eng'rs & Contractors,
Inc., 960 S.W.2d 41, 47–48 (Tex. 1998). Here, Fondren’s trial theory was
that Penn’s statement that “all bills would be paid” constituted a
material misrepresentation that DPMC would pay Fondren’s bills owed by
Westbrook in connection with the Briarcliff property. We hold the trial court reasonably
could have concluded that Property Code section 53.201(b) precludes any
suit for fraud against BHDA and DPMC based on testimony at trial, because
Lubkeman admitted that the work he performed was covered by the bond. If the fraud allegation seeks
recovery for amounts owed for work performed that is covered by the bond,
then the bond is Fondren’s exclusive remedy. See Tex. Prop. Code Ann. §
53.201(b). Moreover, BHDA and
DPMC paid all monies they owed to Fondren. It is undisputed that Fondren’s
unpaid balance was pursuant to a contract with Westbrook; thus, any
damages Fondren incurred happened before Hill’s alleged assurances. Therefore, the trial court
reasonably could have concluded that Hill’s representation referred to
amounts owed by the defendants, not Westbrook, and could not be a
proximate cause of the damages Fondren had already incurred as a result of
Westbrook’s failure to pay on its contract with
Fondren. The elements of a negligent misrepresentation
claim are: (1) the defendant made a representation in the course of its
business, or in a transaction in which it had a pecuniary interest; (2)
the defendant supplied false information for the guidance of others in
their business; (3) the defendant did not exercise reasonable care or
competence in obtaining or communicating the information; and (4) the
plaintiff suffered pecuniary loss by justifiably relying on the
representation. Roof Sys.,
Inc. v. Johns Manville Corp., 130 S.W.3d 430, 438 (Tex. App.—Houston
[14th Dist.] 2004, no pet.) (citing Fed. Land Bank Ass’n v. Sloane,
825 S.W.2d 439, 442 (Tex. 1991)).
As with Fondren’s fraud claim, after hearing Fondren’s evidence at
trial, the trial court reasonably could have concluded that no
representation by DPMC was false or caused any losses to Fondren. DPMC paid Fondren all the money it
owed for work done on behalf of DPMC and on behalf of its related entity,
HRI. We therefore hold that
the trial court did not err in granting judgment against Fondren on its
negligent misrepresentation claim. Recovery under a claim of
unjust enrichment requires a plaintiff to prove that the defendant
benefited from him through fraud, duress, or the taking of undue
advantage. Haldenfels
Bros., Inc. v. City of Corpus Christi, 832 S.W.2d 39, 41 (Tex.
1992). Here, DPMC paid
Fondren in full for the work it performed for DPMC, and Fondren presents
no evidence that DPMC was unjustly enriched by work Fondren performed
pursuant to its contract with Westbrook. Thus, the trial court did not err
in granting judgment against Fondren on its unjust enrichment
claim. Accordingly, we hold the trial
court did not err in entering judgment against Fondren on its claims
against BHDA and DPMC. CONCLUSION The trial court properly
granted summary judgment in favor of John Deere because Fondren filed suit
on the payment bond against John Deere outside the limitations period set
forth in the Property Code.
The trial court properly entered judgment in favor of BHDA and DPMC
because the evidence presented by Fondren at the bench trial supports the
existence of a valid payment bond covering the work Fondren performed, and
thus the Property Code precludes a suit against the property or the
property owner. Moreover, the
trial court reasonably could have concluded that Fondren’s evidence at
trial failed to prove at least one element of each of its causes of
action. We affirm the
judgment of the trial court.
Jane Bland
Justice Panel consists of Justices
Taft, Higley, and Bland. [1]
The record contains an original petition
filed in February 2002, asserting the same causes of action against BHDA,
but with a different cause number.
There is no indication, either in the record or in the briefs, as
to any disposition relating to that cause number. The fourth amended petition, along
with the orders, judgments, and notice of appeal, all bear the 2000 cause
number. | ||||||||||||||||||||